Custom Modular Systems

Ford Engine Plant

Project

Ford Engine Plant

Categories

Mechanical, Automotive, Industrial

Client

Ford Motor Company

Location

Windsor, Canada - 2019

Description

300 Horsepower steam boiler plant for process wastewater treatment

Challenge

Company needed a vendor to expedite the delivery and installation of a new boiler plant to replace the aging infrastructure. The entire project timeline was accelerated.

Solution:

  • Flex Air was contracted to complete the design of the steam plant with only bridging documents supplied.
  • Support installation within an accelerated project timeline.
  • Supplied (2) 150 HP steam boilers complete with feed water tank, steam manifolds, and ancillary equipment.
  • Included modular building with 2-hour fire-rated wall.